which one? seenagape 12 years ago [tagged]During qualitative risk analysis you want to define the risk urgency assessment. All of the followingare indicators of risk priority except for which one? A.Cost of the project B.Risk rating C.Warning signs D.Symptoms ← Previous question Next question →