PMI Exam Questions

Which of the following will provide the basis for estimating, scheduling, executing, and monitoring

Which of the following will provide the basis for estimating, scheduling, executing,
and monitoring and controlling project work?

A.
Activities

B.
Milestone list

C.
Work breakdown structure (WBS)

D.
Work packages