PMI Exam Questions

Which of the following will be required to perform simulation for schedule risk analysis?

Which of the following will be required to perform simulation for schedule risk analysis?

A.
Activity list and activity attributes

B.
Schedule network diagram and duration estimates

C.
Schedule data and activity resource requirements

D.
Milestone list and resource breakdown structure