Which of the following terms is used for a schedule compression technique where two activities that

[tagged]
Which of the following terms is used for a schedule compression technique where two activities that were previously scheduled to start sequentially start at the same time?

A.
Fast tracking

B.
Compressing

C.
Float

D.
Crashing