Which of the following strategic considerations often results in project
authorization?

A.
Customer requests and/or issue resolution
B.
Stakeholder expectations and/or strategic opportunity (business need)
C.
Technologicaladvancement and/or senior executive request
D.
Market demand and/or legal requirements