Which of the following risk responses delineates that the project plan will not be changed to deal w seenagape 12 years ago Which of the following risk responses delineates that the project plan will not be changed to dealwith the risk? A.Exploitation B.Transference C.Acceptance D.Mitigation ← Previous question Next question →