PMI Exam Questions

which of the following processes?

[tagged]
The Project Risk Management knowledge area focuses on which of the following processes?
Each correct answer represents a complete solution. Choose all that apply.

A.
Quantitative Risk Analysis

B.
Risk Monitoring and Control

C.
Potential Risk Monitoring

D.
Risk Management Planning