PMI Exam Questions

which of the following processes when they finalize all activities across all of the management pro

A project team is in which of the following processes when they finalize all activities across all of the management process groups to formally complete the project?

A.
Closing

B.
Executing

C.
Monitoring Controlling

D.
Monitoring Controlling