which of the following processes, probability and impact matrix is prepared? seenagape 12 years ago [tagged]During which of the following processes, probability and impact matrix is prepared? A.Perform Qualitative Risk Analysis B.Monitoring and Control Risks C.Plan Risk Responses D.Perform Quantitative Risk Analysis ← Previous question Next question →