which of the following processes, probability and impact matrix is prepared?

[tagged]
During which of the following processes, probability and impact matrix is prepared?

A.
Perform Qualitative Risk Analysis

B.
Monitoring and Control Risks

C.
Plan Risk Responses

D.
Perform Quantitative Risk Analysis