John works as a project manager for ABD project. He and his team, are working on the following
activities:
Relative ranking or priority list of project risks
Watchlists of low priority risk
Trends in Qualitative Risk Analysis results
On which of the following processes is John working on?
A.
Perform Qualitative Risk Analysis
B.
Plan Risk Management
C.
Plan Risk Responses
D.
Perform Quantitative Risk Analysis