[tagged]
You are the project manager of a large construction project. You are evaluating the strengths,
weaknesses, opportunities, and threats involved in a project. In which of the following processes
are you on?
A.
Define Scope
B.
Plan Risk Responses
C.
Plan Risk Management
D.
Identify Risks