Which of the following plans is not done during the writing of a project plan?

Which of the following plans is not done during the writing of a project plan?

A.
Executive Communication

B.
Risk Management

C.
Quality Management

D.
Scope Statement

Explanation:
Executive Communication may be a part of your communication process but not in project plan.