Which of the following outputs from the Schedule Control process aids in the communication of SV, SP seenagape 9 years ago Which of the following outputs from the Schedule Control process aids in thecommunication of SV, SPI or any performance status to stakeholders? A. Performance organizations B. Schedule baselines C. Performance measurements D. Change requests ← Previous question Next question →