Which of the following outputs from the Schedule Contro… seenagape 8 years ago Which of the following outputs from the Schedule Control process aids in the communication of SV, SPI or anyperformance status to stakeholders? A. Performance organizations B. Schedule baselines C. Performance measurements D. Change requests ← Previous question Next question →