PMI Exam Questions

Which of the following outputs from the Control Schedul…

Which of the following outputs from the Control Schedule process aids in the communication of schedule
variance (SV), schedule performance index (SPI), or any performance status to stakeholders?

A.
Performance organizations

B.
Schedule baselines

C.
Work performance measurements

D.
Change requests