which of the following methods? seenagape 8 years ago As part of a mid-project evaluation, your project sponsor has asked you to provide a forecast of total projectcost. You should calculate the forecast using which of the following methods? A. BAC B. EAC C. ETC D. WBS ← Previous question Next question →