which of the following methods? seenagape 9 years ago As part of a mid-project evaluation, your project sponsor has asked you to provide aforecast of total project cost. You should calculate the forecast using which of thefollowing methods? A. BAC B. EAC C. ETC D. WBS ← Previous question Next question →