Which of the following is used to illustrate the connections between work packages or activities and project
team members?

A.
Hierarchical-type charts (HTC)

B.
Organizational breakdown structure (OBS)

C.
Work breakdown structure (WBS)

D.
Responsibility assignment matrix (RAM)