Which of the following is the process of identifying the specific actions to be performed to produce seenagape 9 years ago Which of the following is the process of identifying the specific actions to beperformed to produce the project deliverables? A. Estimate Activity Durations B. Sequence Activities C. Define Activities D. Activity Attributes ← Previous question Next question →