Which of the following is the least helpful input?

You are in process of developing an approximation of the costs of resources needed to complete each schedule activity. Which of the following is the least helpful input?

A.
WBS, WS dictionary

B.
Market place conditions, commercial databases

C.
Estimate Costs policies/ templates, historical information, project team knowledge

D.
Activity cost estimates, activity cost estimate supporting detail