Which of the following is not contained in the project scope statement?

Your company has asked you to be the project manager for the product introduction of its new DeskTop Rock media system. You recently published the project scope statement. Which of the following is not contained in the project scope statement?

A.
Requested changes

B.
Project configuration management requirements

C.
Constraints

D.
Project specifications

Explanation:
Requested changes are an output of the Scope Definition process. They are not part of the project scope statement.