Which of the following is not a part of the project cost baseline but is included in the project budget?
A.
Management Contingency Reserve
B.
Management Overheads
C.
Project Management Planing
D.
Activity Cost Contingency Reserve
Explanation:
The difference between the Cost Baseline and Funding requirement at Project completion is Management Contingency Reserve.
Management Contingency Reserve is not part of project cost baseline.