PMI Exam Questions

Which of the following is generally the MOST CORRECT use of a project network diagram?

Which of the following is generally the MOST CORRECT use of a project network diagram?

A.
Showing the project schedule

B.
Documenting activity interdependencies

C.
Defining project resources

D.
Defining the project costs