Which of the following is described in the statement given below?

[tagged]
Which of the following is described in the statement given below?
β€œIt serves as the primary input for the Plan Program Stakeholder Management process, as well as for the distribution of program reports and other communication.”

A.
Stakeholder register

B.
Program scope statement

C.
Governance plan

D.
Organizational chart