Which of the following is an input to the Direct and Manage Project Execution process? seenagape 10 years ago Which of the following is an input to the Direct and Manage Project Executionprocess? A.Approved change requests B.Approved contract documentation C.Workperformance information D.Rejected change requests ← Previous question Next question →