EAC (estimate at complete) is typically based on actual cost (AC) for work completed plus an ETC (estimate to complete) the remaining work. Which of the following is a valid formula for calculating EAC?
A.
EAC = AC + [(BAC-EV) / (Cumulative CPI * Cumulative SPI)]
B.
EAC = BAC – AC
C.
EAC = 1 – CPI
D.
EAC = EV + [1 – (Cumulative CPI * Cumulative SPI) / BAC]