PMI Exam Questions

Which of the following is a valid formula for calculating EAC?

EAC (estimate at complete) is typically based on actual cost (AC) for work completed plus an ETC (estimate to complete) the remaining work. Which of the following is a valid formula for calculating EAC?

A.
EAC = AC + [(BAC-EV) / (Cumulative CPI * Cumulative SPI)]

B.
EAC = BAC – AC

C.
EAC = 1 – CPI

D.
EAC = EV + [1 – (Cumulative CPI * Cumulative SPI) / BAC]