Which of the following is a tool and technique used in the Develop Schedule process? seenagape 10 years ago Which of the following is a tool and technique used in the Develop Schedule process? A.Three-point estimates B.Resource leveling C.Precedence diagramming method D.Bottom-up estimating ← Previous question Next question →