Which of the following is a schematic display of the project’s schedule activities and the logical seenagape 9 years ago Which of the following is a schematic display of the project’s schedule activities andthe logical relationships among them? A. Gantt chart B. Project schedule network diagram C. Project milestone list D. Activity list ← Previous question Next question →