Which of the following is a measure of the value of work completed compared to the actual cost or pr seenagape 10 years ago Which of the following is a measure of the value of work completed compared to the actual cost orprogress made on the project? A.Schedule performance index (SPI) B.Cost performance index (CPI) C.Cost variance (CV) D.Planned value (PV) ← Previous question Next question →