PMI Exam Questions

Which of the following is a measure of the value of work completed compared to the actual cost or pr

Which of the following is a measure of the value of work completed compared to
the actual cost or progress made on the project?

A.
Schedule performance index (SPI)

B.
Cost performance index (CPI)

C.
Cost variance (CV)

D.
Planned value (PV)