PMI Exam Questions

Which of the following is a measure of the value of wor…

Which of the following is a measure of the value of work completed compared to the actual cost or progress
made on the project?

A.
Schedule performance index (SPI)

B.
Cost performance index (CPI)

C.
Cost variance (CV)

D.
Planned value (PV)