Which of the following is a measure of the value of wor… seenagape 8 years ago Which of the following is a measure of the value of work completed compared to the actual cost or progressmade on the project? A. Schedule performance index (SPI) B. Cost performance index (CPI) C. Cost variance (CV) D. Planned value (PV) ← Previous question Next question →