Which of the following events would result in a baseline update?
A.
Your project is behind schedule and you want your baseline to reflect estimated actual completion.
B.
Your customer has approved a change request broadening the project scope and increasing the budget.
C.
One of the risks identified in the Risk Management Plan occurs resulting in a schedule delay.
D.
One of your key project team resources has left your team and no replacement is available.