PMI Exam Questions

Which of the following events would result in a baseline update?

Which of the following events would result in a baseline update?

A.
Your project is behind schedule and you want your baseline to reflect estimated actual completion.

B.
Your customer has approved a change request broadening the project scope and increasing the budget.

C.
One of the risks identified in the Risk Management Plan occurs resulting in a schedule delay.

D.
One of your key project team resources has left your team and no replacement is available.