Which of the following estimates MOST accurately reflects the actual cost of the project?

Which of the following estimates MOST accurately reflects the actual cost of the project?

A.
Top-down

B.
Bottom-up

C.
Budget

D.
Appropriations

Explanation:
Bottom-up estimating : Estimating the cost of individual work items and then rolling up the costs to arrive at a project total – more accurate