Which of the following documents provides the mandate to execute the program within a certain timeli

[tagged]
Which of the following documents provides the mandate to execute the program within a certain timeline and also presents milestones for the delivery of products or incremental benefits?

A.
Program architecture baseline

B.
Program risk register

C.
Program WBS

D.
Program charter