Which of the following correctly explains the term "progressive elaboration’?

Which of the following correctly explains the term “progressive elaboration’?

A.
Changing project specifications continuously

B.
Elaborate tracking of the project progress

C.
Elaborate tracking of the project specifications with a change control system

D.
Project specifications becoming more explicit and detailed as the project
progresses