Which of the following consists of the detailed project scope statement and its associatedWBSand WBS

Which of the following consists of the detailed project scope statement and its associatedWBSand
WBS dictionary?

A.
Scope plan

B.
Product scope

C.
Scope management plan

D.
Scope baseline