Which of the following can be used to determine what work is included in each work package for each seenagape 13 years ago Which of the following can be used to determine what work is included in each work package for each of your team members? A.None of the choices are correct B.WBS dictionary C.RBS D.Project scope statement ← Previous question Next question →