PMI Exam Questions

Which of the following are NOT tools or techniques of the Activity Definition process?

Which of the following are NOT tools or techniques of the Activity Definition process?

A.
Expert judgment

B.
Decomposition, templates

C.
Rolling wave planning

D.
Schedule network templates