PMI Exam Questions

Which of the following are inputs to Activity Definition?

Which of the following are inputs to Activity Definition?

A.
Project Scope Statement and Work Breakdown Structure

B.
Activity list and Arrow Diagram

C.
Change Requests Lists and Organizational Process Assets

D.
Project Management Plan and Resource Availability