PMI Exam Questions

Which of the following activities is not part of Plan Risk Management?

Which of the following activities is not part of Plan Risk Management?

A.
Updating risk register

B.
Determining risk roles and responsibilities

C.
Identifying risk categories

D.
Developing a risk management plan

Explanation:
Updating the risk register first happens in Identify Risks phase. Determining risk roles and responsibilities, Identifying risk categories and developing a risk management plan are part of Plan Risk Management.