PMI Exam Questions

Which monitoring or controlling activities would not result in preventive action being applied?

Which monitoring or controlling activities would not result in preventive action being applied?

A.
Control Scope

B.
Manage project team

C.
Quality control

D.
Manage Scope statement

Explanation:
Scope, schedule, and Control Costs can all result in corrective action, but not preventive action.