Which modeling technique does NOT provide event-oriented and project-oriented analysis for identifie

[tagged]
You are the project manager of a large project that will last four years. In this project, you would
like to model the risk based on its distribution, impact, and other factors. There are three modeling
techniques that a project manager can use to include both event-oriented and project-oriented
analysis. Which modeling technique does NOT provide event-oriented and project-oriented
analysis for identified risks?

A.
Sensitivity analysis

B.
Jo-Hari Window

C.
Expected monetary value

D.
Modeling and simulation