Which may be employed to shorten a schedule without changing the scope of the task?
A.
Alter to task priorities.
B.
Releasing resources earlier from tasks which were scheduled with a late start.
C.
Fast tracking or Crashing
D.
Fast tracking.
E.
Crashing