Which knowledge area employs the processes required to ensure timely and appropriate generation, col

Which knowledge area employs the processes required to ensure timely and appropriate
generation, collection, distribution, storage, retrieval, and ultimate disposition of project
information?

A.
Project Risk Management

B.
Project Integration Management

C.
Project Communications Management

D.
Project Quality Management