Which knowledge area employs the processes required to ensure timely and
appropriate generation, collection, distribution, storage, retrieval, and ultimate
disposition of project information?

A.
Project Risk Management
B.
Project Integration Management
C.
Project Communications Management
D.
Project Quality Management