Which is the correct formula for calculating expected activity cost for three-point estimating? seenagape 9 years ago Which is the correct formula for calculating expected activity cost for three-pointestimating? A.Ce = (C0 + 6Cm + Cp)/4 B.Ce = (6C0 + Cm + Cp)/4 C.Ce = (C0 + 4Cm + Cp)/6 D.Ce = (C0 + Cā, + 4Cp) / 6 ā Previous question Next question ā