Which is generally the least accurate.
A.
Using stakeholders to predict cost
B.
Parametric modelling
C.
Analogous estimating
D.
Computerized estimating
Explanation:
Analogous estimating : Analogous estimating is also called top-down estimating and uses the actual cost of a previous, similar project as the basis for estimating the cost of the current project.