Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be inv

Which input to the Manage Stakeholder Engagement process provides guidance on
how stakeholders can best be involved in a project?

PrepAway - Latest Free Exam Questions & Answers

A.
Feedback analysis

B.
Stakeholder analysis

C.
Communication management plan

D.
Stakeholder management plan

2 Comments on “Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be inv

  1. Andre_Arn says:

    D
    Stakeholder Management Plan includes:
    – Describes methods and technologies used for communication with stakeholders
    – Determines current level and desired level of stakeholder engagement
    – Describes strategy for managing stakeholders throughout the project life cycle.