Which input to the Manage Stakeholder Engagement process is used to document changes that occur duri seenagape 9 years ago Which input to the Manage Stakeholder Engagement process is used to documentchanges that occur during the project? A. Issue log B. Change log C. Expert judgment D. Change requests ← Previous question Next question →