PMI Exam Questions

Which input to the Manage Stakeholder Engagement proces…

Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best
be involved in a project?

A.
Feedback analysis

B.
Stakeholder analysis

C.
Communication management plan

D.
Stakeholder management plan